News

Home / News / Construction Methods for Steel Structure Building Foundations

Construction Methods for Steel Structure Building Foundations

Time : 2026-01-26

The foundation of a steel structure building is critical for its safety and stability. The construction method is not singular but is determined by a comprehensive analysis of superstructure loads, geotechnical conditions, building function, and economy.Here is a systematic guide covering key steps and primary methods from design to construction.


1. Core Design Principles

The foundation's primary tasks are:

① Safe Load Transfer: To safely transfer all superstructure loads (dead load, live load, wind load, seismic load, etc.) to the underlying soil or bedrock.

② Settlement Control: To ensure uniform settlement and prevent differential settlement that could cause structural cracking or tilting.

③ Geotechnical Adaptation: To select the most suitable foundation type based on the site's geotechnical investigation report.


2. Primary Foundation Types & Construction Methods

A. Spread Footings:Used for single-story or light steel buildings on competent soil.

Method:

① Excavation: Dig pits to the bearing stratum as per design dimensions.

② Lean Concrete Blinding: Pour a plain concrete layer for leveling and load distribution.

③ Rebar & Formwork: Install reinforcement mesh (for bending resistance) and foundation formwork.

④ Concrete Pour & Embedment: Cast foundation concrete in one go, accurately embedding anchor bolts or foundation bolts. This is the most critical step for steel column connection; positioning must be extremely precise.

⑤ Curing & Backfilling: After concrete reaches required strength, backfill and compact the soil.


B. Pile Foundations:Used for multi-story or long-span steel buildings on weak/thick soil layers or where settlement control is crucial.

① Precast Piles (e.g., Prestressed Concrete Piles):

Method: Drive or jack factory-precast pile segments into a firm soil layer using a pile hammer or silent piler.

Advantage: Fast construction, consistent quality.


② Cast-in-Place Piles (Bored Piles):

Method: Drill a hole → lower a reinforcement cage → tremie concrete to form the pile.

Pile Cap Construction: Excavate around pile heads, cast a reinforced concrete pile cap (grade beam) to group piles, and embed anchor bolts in the cap.


③ Steel Piles (H-piles, Pipe Piles):

Method: Driven directly into the ground. The steel column can be welded or bolted directly to the pile.

Advantage: Very fast, often used for temporary structures or in very soft soil.


C. Raft (Mat) Foundations:Used when soil bearing capacity is moderate, loads are heavy/uniform, or a basement is required.

Method:

① Bulk Excavation: Excavate the entire building area to the required depth.

② Thick Slab Construction: Install a large, double-layer rebar mat and cast a thick, monolithic reinforced concrete slab (the raft).

③ Embedment: Precisely embed column anchor bolts or shear studs within the raft.

④ Advantage: Excellent integrity, effectively redistributing loads and minimizing differential settlement—acting like a "raft" supporting the entire building.


3. Key Construction Steps & Technical Requirements

① Geotechnical Investigation:

Mandatory first step. Obtain soil stratification, bearing capacity, groundwater level, etc., via drilling, sampling, and lab tests. This is the sole basis for design.

② Excavation & Shoring:

Use sloping, sheet piling, or soldier piles based on excavation depth and site constraints to ensure trench safety.

③ Dewatering:

Employ ditch drains or well-point systems to keep the construction area dry.

④ Reinforcement & Formwork:

Strictly follow drawings for rebar size, spacing, and cover. Formwork must be rigid, tight, and dimensionally accurate.

⑤ Precision Embedding of Anchor Bolts:

The most critical activity. Use dedicated steel bolt fixing templates/jigs to securely hold the bolt group in the exact design position. Tolerances for location, elevation, and plumb are typically within ±2mm. Protect bolts from displacement during concrete pouring.

⑥ Concrete Pouring & Curing:

Pour continuously, vibrate thoroughly to avoid honeycombs. Cure properly under moist covers. Allow concrete to reach specified strength before erecting steel.

⑦ Foundation Inspection & Handover:

Key checks: Concrete test reports, alignment, elevation, anchor bolt tolerance, and surface quality. Steel erection can only begin after approval.


4.Steel Column-to-Foundation Connection Details

After the foundation is complete, the steel superstructure is connected via:

① Exposed Column Base: Anchor bolts protrude; the column is placed and nuts are tightened. Most common, allows for adjustment.

② Embedded Column Base: Part of the steel column is buried in concrete. Offers excellent performance for heavy industrial structures.

③ Grouted Column Base: Steel column sits on a leveling plate; the pocket is filled with non-shrink grout. Common for high-rise buildings.

 

Summary & Recommendations


Sequence: Investigate → Design → Excavate & Dewater → Construct Foundation (by type) → Precision Embedding → Cure & Inspect → Erect Steel.

Core Focus: Anchor bolt accuracy and in-situ concrete quality.

Safety: Trench safety is paramount.

Professional Team: Always involve licensed geotechnical engineers, structural designers, and qualified contractors. Never proceed based on guesswork.For any specific project, it is imperative to have a qualified structural engineer design the foundations based on a detailed site investigation, and to execute construction strictly per approved drawings and codes


Prev

None

Next

Z-Type Folding Container House

Latest news

Construction Methods for Steel Structure Building Foundations

Construction Methods for Steel Structure Building Foundations

The foundation of a steel structure building is critical for its safety and stability. The construction method is not singular but is determined by a comprehensive analysis of superstructure loads, geotechnical conditions, building function, and economy.

Read More
Z-Type Folding Container House

Z-Type Folding Container House

Z-Type Folding Container House—a flat-pack unit that unfolds in minutes to create a fully-finished, insulated living or office space. One 40'HQ can load six units.

Read More